A Liquidated Damages Clause Does Not Oust The Need To Prove The Loss: Bombay HC

The case provides guidance on a party's obligation to plead and prove actual loss even in a scenario where the contract stipulates grant of liquidated damages.

IndiaCorporate/Commercial Law
  • In a claim for liquidated damages, evidence has to be led in support of the same, and such a claim shall be granted on consideration of the basic principles for grant of liquidated damages.
  • Relying on precedents, the High Court has reaffirmed that (a) the amount stipulated as liquidated damages has to be a reasonable compensation and a genuine pre-estimate of damages; (b) should not exceed the amount so stated, or the penalty so prescribed;
  • The actual loss or injury has to be proved for claiming liquidated damages, and such burden may be dispensed with only when actual damage from breach of contract cannot be proved or calculated. 

Introduction

Recently in Raheja Universal Pvt. Ltd. ("Appellant") v. B.E. Bilimoria & Co. Ltd.1 ("Respondent"), the Bombay High Court ("High Court") elaborated on the scope and implications of liquidated damages under Section 74 of the Indian Contract Act 1872 ("Contract Act") and concluded that the actual loss or injury has