Share on LinkedInShare on LinkedIn

ARTICLE · 11 DECEMBER 2025

The Client’s Duty To Inform: Its Scope And Limitations

In its decision Construction BSL Inc. v. Attorney General of Quebec – Ministère des Transports du Québec, the Court of Appeal reminds general contractors that the success of a project depends not only on expertise on the construction site, but also on the client sharing all their expertise and essential information from the tender stage onwards. In the construction industry, transparency is becoming the primary risk management tool.

CanadaReal Estate and Construction

Judgment discussed: Construction BSL Inc. v. Attorney General of Quebec-Ministry of Transport of Quebec, 2025 QCCA 1438

In its decision Construction BSL Inc. v. Attorney General of Quebec – Ministère des Transports du Québec, the Court of Appeal reminds general contractors that the success of a project depends not only on expertise on the construction site, but also on the client sharing all their expertise and essential information from the tender stage onwards. In the construction industry, transparency is becoming the primary risk management tool.

Background

The Ministère des Transports du Québec (MTQ) awarded a bridge repair contract to a contractor following a public call for tenders. During the work, a significant amount of water appeared, requiring extensive pumping work. The contractor informed the MTQ that they could not have anticipated this situation and filed a reimbursement claim for the additional costs.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.