Tenoes Construction v Pinto: The Importance Of Compliance With Timetables In Construction Lien Actions

Singleton Urquhart Reynolds Vogel LLP
Singleton Urquhart Reynolds Vogel LLP
Contributor
Singleton Urquhart Reynolds Vogel LLP

Singleton Urquhart Reynolds Vogel LLP

Singleton Urquhart Reynolds Vogel LLP is a Canadian national law firm that specializes in the...

View firm profile
Explore more from Singleton Urquhart Reynolds Vogel LLP

In Tenoes, Tenoes Construction – the lien claimant, who was a sole proprietorship without legal representation given their lawyer's "recent" removal from the record ...

CanadaReal Estate and Construction

In Ontario, the Superior Court has repeatedly signaled to construction industry litigants that timetables in a lien action (and court proceedings in general) are not mere suggestions; instead, they are an order of the Court in respect of which parties must make honest and meaningful efforts to comply.1 While it may appear common sense to counsel who frequently follow such timetables, the Court's recent ruling in Tenoes Construction v Pinto2 ("Tenoes") has reiterated the significance of following such ordered timetables by confirming that any schedule non-compliance with in lien actions can and will likely have severe consequences for lien claimants, including the discharge of a lien and dismissal of a claim.3