Share on LinkedInShare on LinkedIn

ARTICLE · 22 SEPTEMBER 2016

Supreme Court Of Canada Provides Guidance On Interpretation Of Insurance Policies

The Supreme Court of Canada has provided important guidance in Ledcor Construction Ltd. v Northbridge Indemnity Insurance Co. on interpreting insurance policies, particularly in the context of construction projects.

CanadaReal Estate and Construction

The Supreme Court of Canada has provided important guidance in Ledcor Construction Ltd. v Northbridge Indemnity Insurance Co.1 on interpreting insurance policies, particularly in the context of construction projects.


Background

The source of this litigation was the construction of a 28-storey office building in downtown Edmonton. As one of the final steps in the project, the general contractor retained a subcontractor to clean the tower's exterior windows for $45,000. Unfortunately, the subcontractor used improper tools and methods and ended up scratching the tower's windows to the point where they had to be replaced at a cost of $2.5 million.

The general contractor and subcontractor made a claim under the project's builder's risk policy for the cost of replacing the scratched windows. The policy covered all risks of direct physical loss or damage to the property undergoing construction, subject to certain exclusions. The insurer denied the claim on the basis