In Alberta, where a contractor is of the opinion that the work
under its contract is substantially performed, the contractor may
issue and deliver to the owner a certificate of substantial
performance ("CSP") in respect of the contract. Taking
this step allows a contractor to receive payment of the statutory
10% holdback prior to its work under the contract being totally
complete.
The Builders' Lien Act requires that any CSP issued
by a contractor be posted at the project site within 3 days of
being issued. This posting provides notice to subcontractors and
suppliers that the 45 day clock has started counting down to the
date an owner will be able to release the 10% holdback to the
contractor, provided no liens are registered. Any liens registered
after the expiry of the 45th day and the payment of the
10% holdback to the contractor will only attach to the minor lien
fund, invariably a much smaller pot of money.