On March 20, 2020, the Ontario government introduced an
emergency order under the Emergency Management and Civil
Protection Act which suspended the running of limitation
periods, including those under the Construction Act,
by way of Ontario Regulation 73/20
(the
"Regulation"). The suspension was
retroactive to March 16, 2020.
One of the perhaps unintended consequences of this order was the
suspension of the deadline for suppliers of goods and services on
construction projects to register / perfect a lien
("Lien Periods"). By suspending the Lien
Periods owners could no longer release holdbacks on construction
projects without the risk of having a supplier of goods or services
lien the subject property after release of the holdback –
resulting in adverse consequences to the owner who may have to pay
additional amounts for the same supply of goods and or
services.