Ontario Lifting Suspension Of Lien Periods

Dickinson Wright PLLC
Dickinson Wright PLLC
Contributor
Dickinson Wright PLLC

Dickinson Wright PLLC

Dickinson Wright is a full-service law firm with more than 550 lawyers, serving clients across the...

View firm profile
Explore more from Dickinson Wright PLLC

On March 20, 2020, the Ontario government introduced an emergency order under the Emergency Management and Civil Protection Act which suspended the running of limitation periods, including those under the Construction Act...

CanadaReal Estate and Construction

On March 20, 2020, the Ontario government introduced an emergency order under the Emergency Management and Civil Protection Act which suspended the running of limitation periods, including those under the Construction Act, by way of Ontario Regulation 73/20   (the "Regulation"). The suspension was retroactive to March 16, 2020.

One of the perhaps unintended consequences of this order was the suspension of the deadline for suppliers of goods and services on construction projects to register / perfect a lien ("Lien Periods"). By suspending the Lien Periods owners could no longer release holdbacks on construction projects without the risk of having a supplier of goods or services lien the subject property after release of the holdback – resulting in adverse consequences to the owner who may have to pay additional amounts for the same supply of goods and or services.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from