The Construction Act (Ontario) (formerly known as the
Construction Lien Act) (the "Act") was
substantially amended last year. The first phase of those
amendments came into force in Ontario July 1, 2018. Under the Act
as it existed prior to July 1 (the "Old Act"), landlords
did not need to concern themselves with the potential for liens
arising out of work carried out by tenants.
Under the Old Act, if a tenant contracted for improvements to
its premises it was only the leasehold interest of the tenant that
was exposed to the risk of claims for lien being made my unpaid
contractors and subcontractors. Section 19(1) of the Old Act
provided a mechanism whereby the contractor engaged by a tenant
could give a notice to the landlord regarding the proposed
improvements. If the landlord failed to respond within 15 days,
advising the contactor that the landlord would not assume any
responsibility for the improvement, the landlord's interest
would be exposed to claims for lien.