ARTICLE · 20 JANUARY 2006

Ontario Court Gives Contractors a Break with Standard but Strict Notice and Record Keeping Provisions

Borden Ladner Gervais LLP
Borden Ladner Gervais LLP
Contributor
Borden Ladner Gervais LLP

Borden Ladner Gervais LLP

With over 750 lawyers, intellectual property agents and other professionals, BLG services...

View firm profile
Explore more from Borden Ladner Gervais LLP

Mar-King Construction Company Limited and Dibco Underground Limited v The Regional Municipality of Peel et al, the Ontario Superior Court of Justice refused to dismiss a contractor’s claim on the basis that the contractor had, according to the owner, failed to meet the strict notice and record keeping provisions set out in the contract.

CanadaReal Estate and Construction

By Coleen M Shannon1

Overview

In Mar-King Construction Company Limited and Dibco Underground Limited v The Regional Municipality of Peel et al2, the Ontario Superior Court of Justice refused to dismiss a contractor’s claim on the basis that the contractor had, according to the owner, failed to meet the strict notice and record keeping provisions set out in the contract. 3 However, as this was an interim motion, the ultimate outcome of the trial may be different

Background Facts

In 1999 Mar-King Construction Company ("Mar-King") entered into a $25 million contract with The Regional Municipality of Peel ("Peel") for the construction of a sewer, partly in open cut sections and partly through a tunnel section Problems arose when hard rock conditions wer encountered that significantly increased the costs of construction and the length of time it took to complete the project Claims for these increased costs under the contract were denied and litigation ensued