The recent decision of the Court of Appeal for Ontario in Huether v Sharpe, 2025 ONCA 140, clarifies what constitutes a "continuous act or omission"...

CanadaReal Estate and Construction

The recent decision of the Court of Appeal for Ontario in Huether v Sharpe, 2025 ONCA 140, clarifies what constitutes a "continuous act or omission" that is sufficient to toll the running of the 15-year ultimate limitation period in s.15(2) of the Limitations Act (Act).

Background

The Township of McMurrich Monteith (Township) issued a building permit (Permit) for the construction of a dwelling in 1986. Inspections conducted by the Township during construction found various deficiencies which were noted on an Order to Comply. The Order contained a handwritten note which stated "all complied with". In 1988, the Township issued a treasurer's certificate to the property's new owners which indicated that there were no outstanding work orders against the property. In October 2021, the property was purchased by the plaintiffs who discovered construction defects in the property and issued an action as against the Township in February 2022.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from