Ledcor: Taming Sattva's Wild Horse Of Contractual Interpretation For Standard Form Contracts

The Supreme Court of Canada's unanimous decision of Sattva v. Capital Corp. v. Creston Moly Corp., 2014 SCC 53 opened the barn door and let loose a wild horse in terms of the scope...

CanadaReal Estate and Construction

The Supreme Court of Canada's unanimous decision of Sattva v. Capital Corp. v. Creston Moly Corp., 2014 SCC 53 opened the barn door and let loose a wild horse in terms of the scope and the availability of the use of the surrounding circumstances in contract interpretation. According to Sattva, contractual interpretation was no longer a question of law, but one of mixed fact and law, dependent upon the specific circumstances existing at the time of contract creation. The Court defined the surrounding circumstances very broadly as being "absolutely anything which would have affected the way in which the language of the document would have been understood by a reasonable [person]."

The newly rendered Ledcor Construction Ltd. v. Northbridge Indemnity Insurance Co., 2016 SCC 37 decision appears to be attempt to tame that wild horse—at least where standard form contracts are in play. Prior to Ledcor, appellate and trial courts struggled with the question of how standard

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from