ARTICLE · 28 NOVEMBER 2025

In Your View: Additional Indemnity Clause Or Penalty Clause?

In a judgment rendered on April 25, 2025, the Superior Court ruled on the validity of a clause allowing the client to unilaterally terminate the contract. This clause provided that, in the event of termination, the client had to pay the contractor a lump-sum indemnity equivalent to 25% of the value of the work remaining to be performed.

CanadaReal Estate and Construction

Case comment: Haus Construction Design Inc. v. Gestion Globale Bourque Inc., 2025 QCCS 1370

The contexte

In a judgment rendered on April 25, 2025, the Superior Court ruled on the validity of a clause allowing the client to unilaterally terminate the contract. This clause provided that, in the event of termination, the client had to pay the contractor a lump-sum indemnity equivalent to 25% of the value of the work remaining to be performed.

A client and a contractor had entered into a construction contract for a six-unit residential building. At one point, the client decided to terminate the contract by sending the contractor a notice of termination relying on a clause in the contract.

Upon receiving this notice, the contractor, referring to the same clause, claimed an amount as additional indemnity. The client challenged this claim. In the client’s view, the clause had no legal effect, as it constituted a penalty clause. Moreover, it was allegedly abusive.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from