Case comment: Haus Construction Design Inc. v. Gestion Globale Bourque Inc., 2025 QCCS 1370
The contexte
In a judgment rendered on April 25, 2025, the Superior Court ruled on the validity of a clause allowing the client to unilaterally terminate the contract. This clause provided that, in the event of termination, the client had to pay the contractor a lump-sum indemnity equivalent to 25% of the value of the work remaining to be performed.
A client and a contractor had entered into a construction contract for a six-unit residential building. At one point, the client decided to terminate the contract by sending the contractor a notice of termination relying on a clause in the contract.
Upon receiving this notice, the contractor, referring to the same clause, claimed an amount as additional indemnity. The client challenged this claim. In the client’s view, the clause had no legal effect, as it constituted a penalty clause. Moreover, it was allegedly abusive.