Holding Back On Holdbacks: ONCA Confirms When Construction Lenders Rank Ahead Of Lien Claimants In Priority Disputes

Torys
Torys
Contributor
Torys

Torys

Torys LLP is an international business law firm that works with clients who expect the best advice...

View firm profile
Explore more from Torys

The Ontario Court of Appeal has clarified how construction lenders and contractors rank in priority disputes when a developer becomes insolvent.

CanadaReal Estate and Construction

In KingSett Mortgage Corporation v. Mapleview Developments Ltd.1, the Ontario Court of Appeal explained the proper interpretation of the holdback provisions in the Construction Act in the context of a developer’s insolvency2. The case involved a priority dispute between a construction lender and two contractors that had filed construction liens. The Court confirmed that, as long as there are no subcontractor lien claims, contractor lien claimants have a priority claim for unpaid holdbacks (calculated against the value of unpaid invoices), but do not have a priority claim for the total value of all holdbacks under the contract.

What you need to know

  • In priority disputes, where there are no outstanding subcontractor lien claims, contractor lien claimants are entitled to receive holdbacks calculated against unpaid invoices only.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from