Fairness Is In The Eye Of The Beholder In The Tender Process

The tender process has long been a staple of the construction industry. Variations of that process, via requests for proposals ("RFPs"), requests for quotations ("RFQs") or other similar processes have also been developed, with varying levels of adherence to the traditional tender model.

CanadaReal Estate and Construction

The tender process has long been a staple of the construction industry. Variations of that process, via requests for proposals ("RFPs"), requests for quotations ("RFQs") or other similar processes have also been developed, with varying levels of adherence to the traditional tender model. These models allow someone putting a project out for bid to include protections for the amount or type of claims an unsuccessful bidder can advance.

One common protection is a "limitation of liability" clause restricting the amount of damages for which an unsuccessful bidder can sue.

Limitation of Liability Clauses Can be Enforceable

Whether a particular limitation of liability clause is enforceable was recently considered by the Yukon Court of Appeal in Mega Reporting Inc. v. Yukon (Government of), 2018 YKCA 10.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from