Concurrency Clarified: Ontario Superior Court Of Justice Favours Flexible, Practical Approach To Assessing Concurrent Delays

Singleton Urquhart Reynolds Vogel LLP
Singleton Urquhart Reynolds Vogel LLP
Contributor
Singleton Urquhart Reynolds Vogel LLP

Singleton Urquhart Reynolds Vogel LLP

Singleton Urquhart Reynolds Vogel LLP is a Canadian national law firm that specializes in the...

View firm profile
Explore more from Singleton Urquhart Reynolds Vogel LLP

The Court has also confirmed that to be considered "concurrent", delays may overlap, but need not be identical in duration.

CanadaReal Estate and Construction

The Ontario Superior Court of Justice has confirmed that a realistic, practical approach should be adopted in allocating fault and damages arising from concurrent delays involving multiple project participants. The Court has also confirmed that to be considered "concurrent", delays may overlap, but need not be identical in duration.

The Court's Approach

In the recent case of Schindler Elevator Corporation v. Walsh Construction Company of Canada,1 the Court considered damages arising from alleged concurrent delays caused by a number of subcontractors, including Schindler Elevator Corporation ("Schindler"), in relation to the construction of the Women's College Hospital Capital Redevelopment Project (the "Project"). Schindler made a claim against the design-builder, Walsh Construction/Bondfield Partnership ("WBP") on this P3 Project, for unpaid amounts. WBP counterclaimed and sought set-off against Schindler for, inter alia, damages arising from delays. WBP