Clock's Ticking – 3 Gill Homes Inc. v. 5009796 Ontario Inc. (Kassar Homes), 'Time Is Of The Essence' Clauses And "Harsh" Outcomes

Singleton Urquhart Reynolds Vogel LLP
Singleton Urquhart Reynolds Vogel LLP
Contributor
Singleton Urquhart Reynolds Vogel LLP

Singleton Urquhart Reynolds Vogel LLP

Singleton Urquhart Reynolds Vogel LLP is a Canadian national law firm that specializes in the...

View firm profile
Explore more from Singleton Urquhart Reynolds Vogel LLP

The APS at issue was scheduled to close on August 31, 2021, but experienced construction delays which prevented the closing as set out in the terms of the APS.

CanadaReal Estate and Construction

The Court of Appeal for Ontario's recent decision in 3 Gill Homes Inc. v. 5009796 Ontario Inc. (Kassar Homes) ("3 Gill Homes")1 reminds parties to a contract that breach of a "time is of the essence clause" – even a breach by a matter of minutes – is sufficient to justify termination of the contract.

Although the Court's reasons are straightforward and apply the well-accepted rules of contractual interpretation, this decision nevertheless raises certain questions as to the nature of a termination on such a strict reading of the contract, which we consider below.

Factual Background

On July 4, 2020, the appellant entered into three agreements for purchase and sale ("APS") for the construction of three separate residential homes. While two of the APSs closed without issue, the third (which was the subject of this appeal) did not.