Claim Against Township For Failing To Monitor Building Permit Dismissed Under Ultimate Limitation Period (Huether v. Sharpe)

The Ontario Limitations Act, 2002 (the "Act"), provides for an "ultimate" limitation period of 15 years to commence most types of civil claims.

CanadaReal Estate and Construction

The Ontario Limitations Act, 2002 (the "Act"), provides for an "ultimate" limitation period of 15 years to commence most types of civil claims. Specifically, section 15(2) of the Act provides that "No proceeding shall be commenced in respect of any claim after the 15th anniversary of the day on which the act or omission on which the claim is based took place." While the date of an act or omission may often be evident, where the claim concerns an ongoing issue, it may not be clear when the "act or omission" took place or ended.

In Huether v. Sharpe, 2025 ONCA 140, the Court of Appeal for Ontario addressed the ultimate limitation period for a claim against a municipality for failing to monitor an open building permit.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from