In the recent decision of More v. 1362279 Ontario Ltd. (Seiko Homes)1 ("More"), the Ontario Court of Appeal considered the issue of whether relying on a "time is of the essence" clause...

CanadaReal Estate and Construction

Case Comment: More v. 1362279 Ontario Ltd. (Seiko Homes), 2023 ONCA 527

Introduction

In the recent decision of More v. 1362279 Ontario Ltd. (Seiko Homes)1 ("More"), the Ontario Court of Appeal considered the issue of whether relying on a "time is of the essence" clause to terminate a real estate agreement without a specified closing time constitutes an anticipatory breach of a contract.

Ultimately, the Court in More held that the vendor's actions had constituted an anticipatory breach and also described the vendor as having acted in bad faith. This decision is a helpful reminder to real estate solicitors of the importance of including a specific closing time in agreements of purchase and sale. However, it is important to clarify that this decision does not provide a new interpretation of the "time is of the essence" clause, as other recent case comments have suggested.2 Rather, it was the Court's plain application of the long-established doctrine of

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.