Share on LinkedInShare on LinkedIn

ARTICLE · 12 SEPTEMBER 2023

Sometimes Even When You Win, You Lose: Court Of Appeal Confirms Independent Contractors Have Duty To Mitigate

In Monterosso v. Metro Freightliner Hamilton Inc., 2023 ONCA 413, the Court of Appeal accepted the employer's argument that independent contractors, unlike employees...

CanadaLitigation, Mediation & Arbitration

Bottom Line

In Monterosso v. Metro Freightliner Hamilton Inc., 2023 ONCA 413, the Court of Appeal accepted the employer's argument that independent contractors, unlike employees, have a duty to mitigate when a fixed-term contract is terminated before the end of its term. This did not help the employer as the Court ultimately concluded that the independent contractor in this case satisfied his duty to mitigate.

Background Facts

Antonio Monterosso (the "Contractor") entered into a 72-month fixed-term contract to provide services to Metro Freightliner Hamilton Inc. ("Metro") as an independent contractor. The contract did not contain an early termination clause permitting Metro to terminate the contract early, nor did it include any language requiring the Contractor to mitigate any damages if Metro terminated the contract.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.