Ontario Court Of Appeal Clarifies Approach To Dispute Resolution Timelines

Gowling WLG
Gowling WLG
Contributor
Gowling WLG

Gowling WLG

The firm The firm’s lawyers speak English, French, Russian and Ukrainian. The firm’s client base...

View firm profile
Explore more from Gowling WLG

The Ontario Court of Appeal recently found that a time period in a construction contract for mediation served as a resolution period and not a required precondition for escalating...

CanadaLitigation, Mediation & Arbitration

The Ontario Court of Appeal recently found that a time period in a construction contract for mediation served as a resolution period and not a required precondition for escalating the dispute to arbitration.

Most construction contracts contain a dispute resolution provision. Often these provisions include timelines for key steps in the dispute resolution process such as providing notice of a claim or of a dispute, submitting a claim, responding to a claim or notice of dispute, submitting a dispute to mediation or arbitration, or initiating a court proceeding.

Sometimes, these timelines are deadlines which require a party to take an action within a certain number of days. Sometimes, these timelines set a minimum time period that a party must wait before taking an action.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from