The British Columbia Supreme Court in MRC Total Build Ltd. v F&M Installations
Ltd., 2019 BCSC 765 [MRC Total Build] recently
considered an application by a general contractor to stay
proceedings commenced by a subcontractor and refer the matter to
arbitration where the relevant subcontract between them did not
contain an express arbitration clause, but instead generally
incorporated by reference the prime contract between the general
contractor and the owner into the subcontract.
In particular, the prime contract contained a mandatory
arbitration clause, as well as a provision requiring the general
contractor to incorporate by reference all terms and conditions of
the prime contract into all subcontracts. The relevant subcontract
included a clause stating that the "Prime Contract, associated
drawings and specifications for the scope of work are attached in
Schedule I and form part of this Subcontract Agreement."
However, while the subcontract expressly referenced a