Introduction
In Prime Time (Abby Lane) Inc. v. DGBK Architects,
2022 BCSC 1799 (“Prime Time”), the BC Supreme
Court answered the long-standing question of whether it is
appropriate to commence a third-party claim by way of a separate
notice of civil claim. The court ultimately decided that
third-party claims can indeed be brought by way of a separate
notice of civil claim.
Background facts
This matter involved three actions, with the main action
concerning alleged breaches of contract and negligence by multiple
consultants in connection with the construction of a building in
Surrey. Eckford Tyacke + Associates and Eckford & Associates
Landscape Architecture Inc. (“Eckford”) and DGBK
Architects, Greg Dowling Architect Inc., Sebastian Butler Architect
Inc., Ralf Janus Architect Incorporated, Robert Lange Architect
Inc., and Sebastian Butler ( collectively, “DGBK”) were
two of the defendants in the main action. They filed separate
notices of civil claim seeking