Appeal On Counterclaim Judgment In Construction Lien Act Proceeding Goes To Divisional Court Even When Lien Discharged Before Trial

The decision emerged from an unusual procedural history. The plaintiff's claim for a lien was struck out, and the lien was discharged, due to failure to answer undertakings and refusals.

CanadaLitigation, Mediation & Arbitration

In TRS Components Ltd. v. Devlan Construction Ltd., released April 29, 2015, the Ontario Court of Appeal held that the judgment on a counterclaim brought in a claim commenced under the Construction Lien Act is a judgment "under the [Construction Lien] Act" even when the lien itself was discharged, and the claim for lien dismissed, before trial. This is important as the appeal of such a judgment will proceed to the Divisional Court instead of the Court of Appeal.

Background

The decision emerged from an unusual procedural history. The plaintiff's claim for a lien was struck out, and the lien was discharged, due to failure to answer undertakings and refusals. However, the defendant's counterclaim proceeded to trial and the defendant obtained judgment for nearly $70,000. The plaintiff appealed the judgment on the counterclaim to the Court of Appeal.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from