ARTICLE · 05 MAY 2021

No "Do-Overs": Even If The Government Provides Confusing Information, Bidders Remain Responsible For Meeting Bid Dispute Filing Deadlines

Two recent Canadian International Trade Tribunal (CITT) cases have once again re-emphasized to bidders that the 10-day complaint submission deadline under the Tribunal's procurement regulations...

CanadaGovernment, Public Sector

Two recent Canadian International Trade Tribunal (CITT) cases have once again re-emphasized to bidders that the 10-day complaint submission deadline under the Tribunal's procurement regulations will be strictly enforced. 

In Nur Construction Ltd v PWGSC1, Nur was unsuccessful in its bid for the provision of maintenance services for Canadian Forces housing at CFB Borden. In the Public Services and Procurement Canada (PSPC) 2 regret letter, bidders were advised:

"If you have any concerns relating to the procurement process, please refer to the Recourse Mechanisms page on the Buyandsell.gc.ca website. Please note that there are strict deadlines for filing complaints with the Canadian International Trade Tribunal (CITT) or the Office of the Procurement Ombudsman (OPO), where applicable."

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from