On November 10, 2010, Suncor Energy Services Inc.’s Kent Breeze 20 MW eight-turbine wind farm in Chatham-Kent, Ontario, received the first Renewable Energy Approval (REA) pursuant to Ontario’s Green Energy Act.

CanadaEnergy and Natural Resources

On November 10, 2010, Suncor Energy Services Inc.'s Kent Breeze 20 MW eight-turbine wind farm in Chatham-Kent, Ontario, received the first Renewable Energy Approval (REA) pursuant to Ontario's Green Energy Act. The REA has been appealed to the Ontario Environmental Review Tribunal (ERT), and the hearing is scheduled to begin February 1, 2011. We will provide updates to you about the appeal.

Background

To succeed, the applicants (local residents) must meet an onerous test under the Ontario Environmental Protection Act. Specifically, the applicants must establish that it is more likely than not that the wind farm will cause (i) serious harm to human health, or (ii) serious and irreversible harm to plant life, animal life or the natural environment.