Hydro-Québec v. Construction Polaris Inc. 2019 QCCA
990
http://canlii.ca/t/j0ttm
Polaris obtained from HQ a contract to build a road leading to
the La Romaine hydroelectric facility. Quickly, cost overruns occur
and, gradually, Polaris claims an amount of 24.7M$ from HQ. HQ
demands an audit, fully supported by forensic documentation in
support of the additional costs. During this time, Polaris is
experiencing financial problems precisely because it was faced with
these unsuspected costs it had to finance all the while continuing
to build the road. The bank recalled the financing and revolving
credit. The situation became dire and Polaris faced bankruptcy.
A meeting took place between HQ, Polaris and its surety, Axa.
Polaris was looking for an immediate payment of 4M$ by HQ to avoid
bankruptcy and allow it to complete the project while the parties
analyzed the merits of the 24.7M$ claim. However, at this meeting,
HQ asked Polaris to accept a one-time payment of