NESO And Early Competition: Further Developments Explained

Gowling WLG
Gowling WLG
Contributor
Gowling WLG

Gowling WLG

The firm The firm’s lawyers speak English, French, Russian and Ukrainian. The firm’s client base...

View firm profile
Explore more from Gowling WLG

In April 2021, NESO published its Early Competition Plan (ECP) setting out its initial strategy for introducing Early Competition (the commercial arrangements...

CanadaAntitrust/Competition Law

In April 2021, NESO published its Early Competition Plan (ECP) setting out its initial strategy for introducing Early Competition (the commercial arrangements that will apply to a Competitively Appointed Transmission Owner (CATO) to finance, build, operate and maintain assets on the onshore electricity transmission network). Ofgem on 21 October 2024 published a consultation on NESO's proposals for how the commercial framework will work and now seeks stakeholder views on their proposals' viability.

Post-award security obligation

The ECP sets out an obligation for the CATO to provide security during the preliminary works period (where the CATO will be looking to obtain necessary planning consents). NESO proposes that security cover should be 10% of the forecast construction costs until Financial Close, with the security requirement being tapered down to 0% once the CATO has invested a specified amount in the project. NESO proposes that acceptable forms of security

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.