Introduction
Timely payment of progress claims is a long-standing issue in the construction industry.
Despite making up about 6 per cent of NSW's gross domestic product, the NSW construction industry accounted for up 20.6% of all companies calling in the administrators over the 2018-19 financial year.
Management and pursuit of outstanding progress claims is essential to avoid cash flow difficulties.
The Building and Construction Industry Security of Payment Act 1999 (NSW) (SOP Act) can help ensure the prompt resolution of disputes and maintain the timely flow of cash to industry contractors.
As previously discussed in Part 1, the SOP Act entitles a person (Claimant) who, under a construction contract, has carried out construction work or supplied related goods and services to make a payment claim to receive a progress payment.