ARTICLE · 11 JUNE 2015

Tough luck: Paying a progress claim the subject of an adjudication application before the determination can result in an overpayment

Corrs Chambers Westgarth
Corrs Chambers Westgarth
Contributor
Corrs Chambers Westgarth

Corrs Chambers Westgarth

Corrs Chambers Westgarth is Australia’s leading independent law firm. We provide exceptional legal...

View firm profile
Explore more from Corrs Chambers Westgarth

This case shows how the courts can construe the purpose and object of the Act to favour contractors and subcontractors.

AustraliaReal Estate and Construction

KEY TAKEAWAYS

There is a perception that the Construction Contracts Act 2004 (WA) (the Act) is weighted in favour of parties who are in 'subordinate' positions on the payment pecking order (generally contractors and subcontractors). The recent Western Australian District Court decision in Kuredale Pty Ltd v John Holland Pty Ltd [2015] WADC 61 arguably reinforces that perception and is an example of how the courts are willing to construe the purpose and object of the Act to favour contractors and subcontractors. This decision also adds to a growing body of case law that provides guidance about the circumstances that will provide a court with 'sufficient reason' to decline to grant leave to enforce adjudication determinations under s 43 of the Act.