Time is of the essence when making claims under the Security of Payment legislation in Victoria!

Holding Redlich
Holding Redlich
Contributor
Holding Redlich

Holding Redlich

Holding Redlich is a large national commercial firm with offices in Melbourne, Canberra, Sydney,...

View firm profile
Explore more from Holding Redlich

This decision highlights that parties seeking to assert their rights under the Act must adhere strictly to time limits.

AustraliaReal Estate and Construction

It is now clear that payment claims served out of time under the Victorian Building and Construction Industry Security of Payment Act (Act) will be invalid after the recent Victorian Supreme Court decision in Hallmarc Construction v Saville [2014] VSC 491.

Facts

Hallmarc Construction entered into a construction contract with Mr Saville for the supply and installation of joinery for a 134-apartment residential development.

The contract between the two parties made no express provision regarding time for payment, defects liability period or a final payment certificate. As a result, the default provisions covering such matters under the Act applied, meaning:

  • the reference date for a final payment claim was the date immediately following the day after the construction work or related goods or services were last carried out (s 9(2)(d) of the Act); and