Share on LinkedInShare on LinkedIn

ARTICLE · 27 OCTOBER 2026

Residential Focus: Loulach Schedules And Tribunal Proceedings

Holding Redlich
Holding Redlich
Contributor
Holding Redlich

Holding Redlich

Holding Redlich is a large national commercial firm with offices in Melbourne, Canberra, Sydney,...

View firm profile
Explore more from Holding Redlich

The NSW Civil and Administrative Tribunal has examined whether modified Scott schedules, known as Loulach schedules, are mandatory in proceedings involving breaches of the statutory duty of care under the Design and Building Practitioners Act 2020. This decision clarifies procedural requirements for construction defect claims in the Tribunal's informal setting, where formal pleadings are not required and the Tribunal must act with minimal formality as circumstances permit.

AustraliaReal Estate and Construction

A recent decision of the NSW Civil and Administrative Tribunal (Tribunal) has considered whether Loulach schedules are required in Tribunal proceedings for breach of the statutory duty of care contained in section 37 of the Design and Building Practitioners Act 2020 (NSW) (DBPA).

Loulach schedules are named for the decision in The Owners - Strata Plan No 87060 v Loulach Developments Pty Ltd (No 2) [2021] NSWSC 1068, which introduced the concept of requiring a modified scott schedule in proceedings under section 37, to include columns identifying:

  • the relevant risk in relation to each defect alleged
  • the precautions that the defendant should have taken in relation to each risk.

Subsequent decisions have developed this requirement further, namely:

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from