Residential Focus: Licensing and insurance no bar to SOPA claim

Holding Redlich
Holding Redlich
Contributor
Holding Redlich

Holding Redlich

Holding Redlich is a large national commercial firm with offices in Melbourne, Canberra, Sydney,...

View firm profile
Explore more from Holding Redlich

A progress claim for residential work under contract (completed to an acceptable standard) is payable even if contractor is unlicensed & uninsured.

AustraliaReal Estate and Construction

In Sunshine East Pty Ltd v CBEM Holdings Pty Ltd [2023] NSWSC 744, the Supreme Court of NSW held that a progress claim for residential work under contract, which has been completed to an acceptable standard, is payable even if a contractor is unlicensed and uninsured under the Home Building Act 1989 (NSW) (HB Act).

Background

The owner (plaintiff) engaged a construction manager to manage the design and construction of various buildings, including two dwellings (works) under a Head Contract Construction Management agreement (Construction Management Contract) which was "for use in non-residential building projects". Notwithstanding the choice of contract, "residential building work" is defined in Schedule 2 of the HB Act as work involved in coordinating the construction of a dwelling.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

This publication does not deal with every important topic or change in law and is not intended to be relied upon as a substitute for legal or other advice that may be relevant to the reader's specific circumstances. If you have found this publication of interest and would like to know more or wish to obtain legal advice relevant to your circumstances please contact one of the named individuals listed.

See more popular content from