Share on LinkedInShare on LinkedIn

ARTICLE · 30 OCTOBER 2019

Residential focus - High Court provides clarity on a builder's entitlement to a quantum meruit claim

Holding Redlich
Holding Redlich
Contributor
Holding Redlich

Holding Redlich

Holding Redlich is a large national commercial firm with offices in Melbourne, Canberra, Sydney,...

View firm profile
Explore more from Holding Redlich

Clarity provided regarding remedies available to contractors after termination of a contract as a consequence of repudiation.

AustraliaReal Estate and Construction

High Court provides clarity on a builder's entitlement to a quantum meruit claim

The High Court of Australia recently provided clarity with respect to the remedies available to contractors following termination of the contract as a consequence of repudiation.

In the decision of Mann v Paterson Constructions Pty Ltd [2019] HCA 32, the High Court held that in addition to damages for breach of contract, the remedy of quantum meruit is available to contractors in circumstances where work is performed work for which the right to payment had not accrued prior to the date of termination. For instance, in circumstances of milestone payments, where the milestone had not been achieved before termination.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

This publication does not deal with every important topic or change in law and is not intended to be relied upon as a substitute for legal or other advice that may be relevant to the reader's specific circumstances. If you have found this publication of interest and would like to know more or wish to obtain legal advice relevant to your circumstances please contact one of the named individuals listed.

See more popular content from