ARTICLE · 21 MAY 2019

Residential Focus: Focus on recent decision by NSW Civil and Administrative Tribunal Appeal Panel

Holding Redlich
Holding Redlich
Contributor
Holding Redlich

Holding Redlich

Holding Redlich is a large national commercial firm with offices in Melbourne, Canberra, Sydney,...

View firm profile
Explore more from Holding Redlich

Article discusses recent NSW CATAP decision, the background, grounds of appeal and findings.

AustraliaReal Estate and Construction

Form or content?

In the recent decision of Builtex Constructions Pty Ltd He [2019] NSWCATAP 95, NSW Civil and Administrative Tribunal Appeal Panel dismissed the appellant Builder's submissions that the respondent Owner repudiated the contract because the Owner failed to provide notice of dispute, hold a dispute resolution meeting, and give a proper notice of default to terminate the contract.

Background

In the Tribunal below, orders had been made awarding the Owner more than $100,000 for breach of statutory warranty and dismissing the builder's quantum meruit claim. The relevant contract was a Master Builders Association residential building contract.

The contract before the Appeal Panel was a Master Builders Association residential building contract. The relevant terms are summarised below:

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

This publication does not deal with every important topic or change in law and is not intended to be relied upon as a substitute for legal or other advice that may be relevant to the reader's specific circumstances. If you have found this publication of interest and would like to know more or wish to obtain legal advice relevant to your circumstances please contact one of the named individuals listed.

See more popular content from