ARTICLE · 15 APRIL 2019

Residential Focus: Date of completion for residential building work in NSW

Holding Redlich
Holding Redlich
Contributor
Holding Redlich

Holding Redlich

Holding Redlich is a large national commercial firm with offices in Melbourne, Canberra, Sydney,...

View firm profile
Explore more from Holding Redlich

As the date of completion triggers the commencement of the statutory warranty periods, its determination is significant.

AustraliaReal Estate and Construction

Date of completion for residential building work

In the recent decision of Ashton v Stevenson [2019] NSWCATAP, the NSW Civil and Administrative Tribunal Appeal Panel (Appeal Panel) considered the application of section 3B of the Home Building Act 1989 (NSW) (the Act), which concerns date of completion of residential building work.

As the date of completion triggers the commencement of the statutory warranty periods, its determination is significant, particularly where there is an argument that proceedings may have been commenced out of time.

Section 3B

Section 3B of the Act provides:

3B Date of completion of residential building work

(1A) This section does not apply to residential building work to which section 3C applies.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

This publication does not deal with every important topic or change in law and is not intended to be relied upon as a substitute for legal or other advice that may be relevant to the reader's specific circumstances. If you have found this publication of interest and would like to know more or wish to obtain legal advice relevant to your circumstances please contact one of the named individuals listed.

See more popular content from