ARTICLE · 25 MAY 2019

Residential Focus - damages for defective works - limitation periods

Holding Redlich
Holding Redlich
Contributor
Holding Redlich

Holding Redlich

Holding Redlich is a large national commercial firm with offices in Melbourne, Canberra, Sydney,...

View firm profile
Explore more from Holding Redlich

The Owners Corporation commenced proceedings for defective works one day prior to the expiry of the limitation period.

AustraliaReal Estate and Construction

What comes first? The transfer application or leave to amend?

In The Owners Strata Plan 83405 v Ralan (Culworth) Pty Limited [2019] NSWSC 578, the Supreme Court of New South Wales refused an application for judicial review of the decision made by the Appeal Panel of the NSW Civil and Administrative Tribunal (Tribunal) regarding an application to transfer the proceedings to the Supreme Court pursuant to Clause 6 of Schedule 4 of the Civil and Administrative Tribunal Act 2013 (NSW) (the CAT Act) as damages exceeded the Tribunal's jurisdictional limit.

Background

The Owners Corporation (OC) commenced proceedings in the Tribunal against the developer for alleged defective works one day prior to the expiry of the limitation period.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

This publication does not deal with every important topic or change in law and is not intended to be relied upon as a substitute for legal or other advice that may be relevant to the reader's specific circumstances. If you have found this publication of interest and would like to know more or wish to obtain legal advice relevant to your circumstances please contact one of the named individuals listed.

See more popular content from