A lack of licence was no problem if an unlicensed builder could procure a properly licensed contractor to do the work.

AustraliaReal Estate and Construction
Eleanor Grounds
Eleanor Grounds
Christopher Aaron Yong
Christopher Aaron Yong
Author LinkedIn connections

No licence? No worries

In Precise Builders (NSW) Pty Ltd v Jones & Krel [2018] NSWCATAP 112 the New South Wales Civil and Administrative Tribunal (the Tribunal) Appeal Panel held that a lack of licence was no barrier to the preferred outcome under s.48MA of the Home Building Act 1989 (the Act), upholding a work order over a money order in circumstances where a builder was not properly licensed, but could procure a properly licensed contractor to do the work.

S.48MA of the Act

By way of reminder, s 48MA of the Act provides:

A court or tribunal determining a building claim involving an allegation of defective residential building work or specialist work by a party to the proceedings (the responsible party) is to have regard to the principle that rectification of the defective work by the responsible party is the preferred outcome. (emphasis added)