Residential Focus - 14 February 2018: Part 1 - Dispute resolution clause

Holding Redlich
Holding Redlich
Contributor
Holding Redlich

Holding Redlich

Holding Redlich is a large national commercial firm with offices in Melbourne, Canberra, Sydney,...

View firm profile
Explore more from Holding Redlich

The Court found that the dispute resolution clause did not provide a clear mechanism for the resolution of a dispute.

AustraliaReal Estate and Construction

In Roberts v Morphett Constructions Pty Ltd [2018] NSWCATAP 33, the New South Wales Civil and Administrative Tribunal (Tribunal) dismissed an appeal by an owner claiming that the builder was unable to terminate a building contract due to failure to comply with the dispute resolution clause.

Facts

The owner raised allegations of defective works and work was suspended in January 2016 while a consultant's report was obtained. Work recommenced in February. In March a mediation was arranged with an inspector from Fair Trading NSW who issued a rectification order.

On 4 April 2016 the builder issued a progress claim, which the owner responded to by a notice listing the disputed items. The builder then issued a formal notice alleging breach of contract due to the owner's failure to pay the progress claim as well as other amounts claimed by the builder. The notice stated payment was required within 10 business days otherwise the builder would terminate the contract. The