The Appeal Court found the Council did not owe a duty of care to the purchasers to alert them to defective building work.

AustraliaReal Estate and Construction

Ku-ring-gai Council v Chan [2017] NSWCA 226

On 7 September 2017 the NSW Court of Appeal handed down its decision in Ku-ring-gai Council v Chan [2017] NSWCA 226. The case is an appeal from Chan v Acres [2015] NSWSC 1885, where the Supreme Court of NSW held that Ku-ring-gai Council (Council) in its capacity as principal certifying authority (PCA) breached its duty of care to new purchasers of a property. On appeal, the Court was required to find whether the appellant Council owed the new owners of the property such a duty to take reasonable care in issuing an occupation certificate to avoid their suffering economic loss as a result of the previous owner-builder's defective building work.