Residential Focus – 4 July 2018: Part 1 - Home building disputes in NSW

Holding Redlich
Holding Redlich
Contributor
Holding Redlich

Holding Redlich

Holding Redlich is a large national commercial firm with offices in Melbourne, Canberra, Sydney,...

View firm profile
Explore more from Holding Redlich

This case provides further guidance on section 48MA of the Home Building Act 1989 (NSW) as it applies to incomplete work.

AustraliaReal Estate and Construction
Eleanor Grounds
Eleanor Grounds
Christopher Aaron Yong
Christopher Aaron Yong
Author LinkedIn connections

Clements v Murphy [2018] NSWCATAP 152

In Clements v Murphy [2018] NSWCATAP 152, the New South Wales Civil and Administrative Tribunal Appeal Panel (Appeal Panel) has provided further guidance on section 48MA of the Home Building Act 1989 (NSW) (the Act), as to whether it applies to incomplete work.

Section 48MA of the Act provides:

"A court or tribunal determining a building claim involving an allegation of defective residential building work or specialist work by a party to the proceedings (the "responsible party") is to have regard to the principle that rectification of the defective work by the responsible party is the preferred outcome."

Facts

The Owners entered into a contract with the Builder to construct a home (Contract). When a dispute arose regarding payment claims lodged by the Builder, the Builder served a notice purporting to terminate the Contract, which the Owners accepted and treated as a repudiation of the Contract.