Share on LinkedInShare on LinkedIn

ARTICLE · 13 JANUARY 2015

Proceedings for defective building work: 2 Elizabeth Bay Road Pty Ltd v The Owners - Strata Plan No 73943 [2014] NSWCA 409

Although the proceedings were commenced in contravention of the NSW legislative requirements, they were not invalid.

AustraliaReal Estate and Construction

The Owner's Corporation of a building in Elizabeth Bay commenced proceedings against the developer for defective building work carried out on common property. It is a requirement of s 80D of the Strata Schemes Management Act 1996 (NSW) that a general meeting of the Owner's Corporation pass a resolution approving the commencement of proceedings, however a resolution was only passed at an annual general meeting after the proceedings had been commenced. The developer sought an order that the proceedings be struck out or dismissed because of the failure to comply with s 80D of the Strata Schemes Management Act 1996 (NSW) by reason of the delay in the passing of the resolution.

The primary judge held that the requirement of s 80D of the Strata Schemes Management Act 1996 (NSW) could be satisfied by a later resolution and that alternatively, the action of commencing proceedings without authority could be later ratified.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from