Out of time and out of play – the new six-year limitation period for strata claims held to not to apply retrospectively

John Goubran & Associates Pty Ltd ACN 070 974 819 v The Owners – Strata Plan 57150 [2026] NSWDC 9

AustraliaReal Estate and Construction

John Goubran & Associates Pty Ltd ACN 070 974 819 v The Owners – Strata Plan 57150 [2026] NSWDC 9.

On 1 July 2025, an amendment to section 106(6) of the Strata Schemes Management Act 2015 (NSW) (Act) came into effect, extending the limitation period to bring claims for reasonably foreseeable loss arising from a breach of the statutory duty to properly repair and maintain the common property contained in section 106(1) of the Act from 2 to 6 years. See our previous Limebite for more information on this amendment.

On 25 February 2026, in John Goubran & Associates Pty Ltd ACN 070 974 819 v The Owners – Strata Plan 57150 [2026] NSWDC 9, Judge Cole found that this limitation period would not operate retrospectively, and only applied to existing rights and obligations as at 1 July 2025.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from