ARTICLE · 18 OCTOBER 2013

No claims under Security of Payment Act if relationship to carry out work has ended, but subcontract is not terminated

Holding Redlich
Holding Redlich
Contributor
Holding Redlich

Holding Redlich

Holding Redlich is a large national commercial firm with offices in Melbourne, Canberra, Sydney,...

View firm profile
Explore more from Holding Redlich

A reference date will not arise after proper termination of a contract (or subcontract), unless it expressly provides.

AustraliaReal Estate and Construction

The Supreme Court decided on 10 October 2013 that in McConnell Dowell v Heavy Plant Leasing that even if a subcontract is not terminated - but the relationship to carry out work is ended (for example, by taking the work out of subcontractor hands) - then no further reference dates arise so Security for Payment claims cannot be made.

Subcontractor payment claims and reference dates: what happens once the subcontract is terminated?

In McConnell Dowell Constructors (Aust) Pty Ltd v Heavy Plant Leasing Pty Ltd [2013] QSC 269, McConnell subcontracted earthworks and civil works to HPL. The subcontract gave McConnell the right to 'determine' HPL's employment in a variety of circumstances, including if HPL appointed an administrator, receiver and manager, and if 'determined', then McConnell would not have to make payment of any monies payable to HPL until the subcontract works were complete.