ARTICLE · 29 OCTOBER 2015

MT HØJGAARD A//S v E.ON Climate and Renewables UK EWCA CIV 407: Fitness for purpose

Corrs Chambers Westgarth
Corrs Chambers Westgarth
Contributor
Corrs Chambers Westgarth

Corrs Chambers Westgarth

Corrs Chambers Westgarth is Australia’s leading independent law firm. We provide exceptional legal...

View firm profile
Explore more from Corrs Chambers Westgarth

This case highlights some difficulties where different design obligations are spread across various contract documents.

AustraliaReal Estate and Construction

KEYWORDS: FITNESS FOR PURPOSE

KEY TAKEAWAY

This case highlights the difficulties that can arise where different design obligations are spread across various arguably inconsistent contract documents.

The issue at the heart of this case is who should pay rectification costs where:

  • the contractor has complied with an established, but incorrect, international design standard; and
  • compliance with the standard means that the contractor cannot satisfy the 20-year fitness for purpose warranty.

The Court was asked to interpret the effect of this specific fitness for purpose warranty, in conjunction with more general warranty provisions. The Court of Appeal overturned the trial Judge's decision, holding that the contractor was not under a "fitness for purpose" obligation and had met the more general requirements of reasonable skill and care by complying with the standard, regardless of the error.