Limitation periods and multiple occupancy permits in Victoria: Court of Appeal confirms first in time applies

Holding Redlich
Holding Redlich
Contributor
Holding Redlich

Holding Redlich

Holding Redlich is a large national commercial firm with offices in Melbourne, Canberra, Sydney,...

View firm profile
Explore more from Holding Redlich

The Court clarified the approach to determining limitation periods for building actions with multiple occupancy permits.

AustraliaReal Estate and Construction

Earlier this month, the Victorian Court of Appeal delivered its judgment which clarified the approach to determining limitation periods for building actions where multiple occupancy permits are issued.

In the decision of Lendlease Engineering Pty Ltd v Owners Corporation No 1 PS526704E [2022] VSCA 105 (Lendlease), the Court of Appeal overturned an earlier Supreme Court decision which held that where multiple occupancy permits are issued for the same building works, the limitation period under section 134 of the Building Act 1993 (Vic) commences on the date of the final occupancy permit for the works.

Earlier Supreme Court decision

The Building Act 1993 (Vic) (Act) provides that a building action cannot be brought more than 10 years after the date of issue of the occupancy permit in respect of the building work carried out.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

This publication does not deal with every important topic or change in law and is not intended to be relied upon as a substitute for legal or other advice that may be relevant to the reader's specific circumstances. If you have found this publication of interest and would like to know more or wish to obtain legal advice relevant to your circumstances please contact one of the named individuals listed.

See more popular content from