Laing O'Rourke Australia Construction Pty Ltd V Samsung C&T Corporation [2016] WASC 49

Corrs Chambers Westgarth
Corrs Chambers Westgarth
Contributor
Corrs Chambers Westgarth

Corrs Chambers Westgarth

Corrs Chambers Westgarth is Australia’s leading independent law firm. We provide exceptional legal...

View firm profile
Explore more from Corrs Chambers Westgarth

Where an injunction will grant final relief, courts apply a higher standard in determining where the balance of convenience lies.

AustraliaReal Estate and Construction

KEYWORDS: INJUNCTIONS; PERFORMANCE BONDS

KEY TAKEAWAY

Where an injunction will have the practical effect of granting final relief, courts apply a higher standard in determining where the balance of convenience lies. This requires balancing the risk of doing an injustice, and the court must be satisfied that the party seeking injunction would ultimately succeed if the matter went to trial.

Facts

Samsung C&T Corporation (Samsung) subcontracted Laing O'Rourke Australia Construction Pty Ltd (LORAC) for structural steel and related works for the port landside package of the Roy Hill Iron Ore Project.

Less than a year later, Samsung terminated the subcontract for its convenience and the parties entered into an Interim Deed under which the bank guarantees LORAC had provided under the subcontract were returned and replaced by another bank guarantee for $7.5 million (Replacement Security).