Friends of Tumblebee Incorporated v ATB Morton Pty Limited (No 2) [2016] NSWLEC 16: Endangered species

Corrs Chambers Westgarth
Corrs Chambers Westgarth
Contributor
Corrs Chambers Westgarth

Corrs Chambers Westgarth

Corrs Chambers Westgarth is Australia’s leading independent law firm. We provide exceptional legal...

View firm profile
Explore more from Corrs Chambers Westgarth

The court declared that a development consent granted was invalid because a Species Impact Statement was not prepared.

AustraliaReal Estate and Construction

On 11 March 2016, Pepper J of the Land and Environment Court (Court) handed down the decision in the matter of Friends of Tumblebee Incorporated v ATB Morton Pty Limited (No 2) [2016] NSWLEC 16, declaring that a development consent granted was invalid because a Species Impact Statement (SIS) was not prepared.

The decision has important implications for developers undertaking developments in areas where endangered species and/or their habitats may be impacted.

SUMMARY & IMPLICATIONS

  • The judgment demonstrates an increasing application of the precautionary principle and consideration of cumulative impacts by the Court in assessing development applications, particularly in the Hunter Valley, for example see Bulga Milbrodale Progress Association Inc v Minister for Planning and Infrastructure and Warkworth Mining Limited [2013] NSWLEC 48.  