Recent case considered length of limitation period and when the limitation period started.

AustraliaReal Estate and Construction

Does 'termination' mean completion of works in Home Building Act warranty claims?

The recent decision in Howell v Talevski clarified that the issue of whether proceedings for breach of the warranties in section 18B of the Home Building Act 1989 (NSW) (HBA) have been commenced within time is ultimately a matter of contractual construction, and that termination of a contract does not render the works complete by relieving the builder of any further obligation to perform the works.

Facts

This case involves a claim by the plaintiff owner (Owner) against the defendant builder and structural engineer (Builder) regarding defective and incomplete work.

In 2007, the parties entered into two contracts. The first, in April 2007, was for the construction of foundations. The second, in May 2007, was for construction of a duplex on those foundations (Contract).

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

This publication does not deal with every important topic or change in law and is not intended to be relied upon as a substitute for legal or other advice that may be relevant to the reader's specific circumstances. If you have found this publication of interest and would like to know more or wish to obtain legal advice relevant to your circumstances please contact one of the named individuals listed.

See more popular content from