Cutting off the dead to save the living - construction contracts: Samsung v Duro [2018] WASCA 27; Duro v Samsung [2018] WASCA 28

Corrs Chambers Westgarth
Corrs Chambers Westgarth
Contributor
Corrs Chambers Westgarth

Corrs Chambers Westgarth

Corrs Chambers Westgarth is Australia’s leading independent law firm. We provide exceptional legal...

View firm profile
Explore more from Corrs Chambers Westgarth

An adjudicator's determination is valid if it is possible to sever any part that suffers from jurisdictional error.

AustraliaReal Estate and Construction

Two recent WA Court of Appeal decisions clarify the scope of an adjudicator's jurisdiction, issues of set-off, and the ability to sever partially invalid determinations in the context of Construction Contracts Act 2004 (WA) (CCA) adjudications.

The decisions are significant; not least because they are two of only five occasions on which the Court of Appeal has turned its mind to the operation of the CCA since it came into operation on 1 January 2005.1

The first decision, Samsung C&T Corporation v Duro Felguera Australia Pty Ltd [2018] WASCA 27 ('Samsung v Duro'), confirms (among other things) that:

  • an adjudicator's duty to dismiss an application without making a determination of its merits (see section 31(2)(a) of the CCA) does not arise if the adjudication concerns a claim for payment for both 'construction work' and non-'construction work';2 but