Contract is king and time bars that bite: CMA Assets Pty Ltd v John Holland Pty Ltd [No 6] [2015] WASC 217

Corrs Chambers Westgarth
Corrs Chambers Westgarth
Contributor
Corrs Chambers Westgarth

Corrs Chambers Westgarth

Corrs Chambers Westgarth is Australia’s leading independent law firm. We provide exceptional legal...

View firm profile
Explore more from Corrs Chambers Westgarth

This case serves as a reminder that clearly drafted time bars will bite if parties do not put their notices in on time.

AustraliaReal Estate and Construction

KEYWORDS: TIME BARS AND PREVENTION PRINCIPLE

KEY TAKEAWAYS

The Western Australian Supreme Court has upheld a strict time bar even where the contractor would otherwise have been entitled to an extension of time. The case serves as a reminder that clearly drafted time bars will bite if parties do not put their notices in on time.

The case also stands for the proposition that a clearly drafted extension of time regime may exclude the operation of the prevention principle (meaning that the contractor will take the risk of accelerating where no extension of time is granted).

The facts

In 2005, BHP engaged the defendant (John Holland) to upgrade and extend a wharf at Finucane Island, Port Hedland. In part, John Holland was required to demolish and reconstruct Berth C. John Holland subcontracted the demolition of Berth C (and the associated berthing and mooring "dolphin" structures unconnected to the wharf) to the plaintiff, (CMA). The project also required