The date work is performed under a contract is only one factor to decide the correct reference date for a payment claim.

AustraliaReal Estate and Construction

KEYWORDS: SECURITY OF PAYMENT; REFERENCE DATES KEY TAKEAWAY

A payment claim served in contravention of section 14(8) of the Building and Construction Industry Security of Payment Act 2002 (Vic) (Act) does not provide a basis for a valid adjudication under the Act.

The date work is performed under a contract is relevant to determining the correct reference date for a payment claim. It is, however, not the only factor for determining the validity of the payment claim.

The facts

Commercial & Industrial Construction Group Pty Ltd (the Plaintiff) in this case sought an order that an adjudication determination made under the Act be quashed or set aside because the relevant payment claim was invalid.